设计简介 |
设计描述:
文档包括:
Word版说明书1份,共147页,约92000字
外文翻译一份
CAD版本图纸,共5张
摘 要
本设计包括三部分:一般部分,专题部分和翻译部分。
一般部分是新阳煤矿5Mt新井设计。全篇共分为十章:矿井概述及井田地质特征、井田境界和储量、矿井工作制度、设计生产能力及服务年限、井田开拓、准备方式-采区巷道布置、采煤方法、井下运输、矿井提升与运输、矿井通风与安全和矿井主要经济技术指标。
新阳煤矿设计年生产能力为5Mt/a,服务年限为63a。矿井工作制度为“四六”制。矿井的采煤方法为走向长壁全部垮落一次采全高综采放顶煤采煤法。
矿井的开拓方式为主斜副立单水平联合开拓。水平标高为+620m,主斜井主要用于提升煤炭,副立井主要用于提升人员、矸石、和材料等。
矿井采用一矿一面的高效作业方式。工作面长度为200m。运输大巷采用胶带运输煤炭,辅助大巷采用无轨胶轮车运输矸石和材料等。区段巷道与上、下山巷道采用Y型联络巷。
矿井通风方式为抽出通风方式,矿井前、后期都采用中央分列式通风。
专题部分主要分析了底板突水的类型和影响因素,运用弹塑性理论研究了煤层底板岩体的破坏深度及底板突水极限压力,同时运用一系列的探测技术对矿井水进行探测为预测及防治煤层底板突水提供了依据。
翻译部分是对美国环境保护协会报告的草稿的总结。它是对现有的和新出现的,能够除去包含在高瓦斯地下煤矿通风空流中的瓦斯的痕迹的技术的评估。题目为:“Mitigation of Methane Emissions from Coal Mine Ventilation Air”。
关键词: 综放工作面; 回采率; Y型联络巷
ABSTRACT
The design includes three parts: the general part of the topic and some of the translation.
General part of XinYang coal-5 Mt design of new wells. The text is divided into ten chapters: Overview of mine and mine geological features, Mine realm and reserves, the mine work, production design and length of service, mine development, preparation methods - mining area roadway layout, mining methods, underground transport, mine Upgrade and transport, safety and mine ventilation shaft and the main economic and technical indicators.
XinYang coal-designed annual production capacity of 5Mt / a, length of service for 63 a. Mine system of work for the "April 6" system. Mining method to mine the long wall to collapse all full-time-high Fully-caving mining method. Mine's pioneering approach, vice ramp mainly single-level and jointly developing legislation. Elevation to the level of +620 m, the main inclined mainly used for upgrading coal, the main shaft for the upgrading of staff, waste and materials.
Use of a mine shaft in a highly efficient operations. Face length of 200 m. Transportation Roadway use tape transport coal, assisted roadway used rubber tire trolley cars and transport of waste materials. The uphill section of roadway by roadway and Y-contact Lane.
Mine ventilation to extract ventilation, mine, have adopted the latter part of the central points out ventilation.
The project section mainly analyses the type of floor water and the influencing factors, using elastic-plastic theory of coal floor rock mass destruction floor water depth and limit pressure, and use of a series of detection techniques to detect the mine water for the prediction and control the water-inrush to provide the basis.
Translation part is to the United States environmental protection association of the summary of the draft report. It is to the existing and new, can remove in underground coal mine ventilation contains way.the gas in the empty flow of technology assessment of trace.,Title:“Mitigation of Methane Emissions from Coal Mine Ventilation Air”。
Key words: Fully-Caving Face ; Recovery rate; Y-contact Lane
目 录
一般设计部分
1 矿区概述及井田地质特征 1
1.1 矿区概述 1
1.2 井田地质特征 3
1.3 煤层特征 11
2 井田境界和储量 19
2.1 井田境界 19
2.2 矿井工业储量 20
2.3 矿井可采储量 22
3 矿井工作制度、设计生产能力及服务年限 26
3.1 矿井工作制度 26
3.2 矿井设计生产能力及服务年限 26
4 井田开拓 28
4.1 井田开拓的基本问题 28
4.2 矿井的基本巷道 34
4.3 主要开拓巷道 39
5 准备方式—盘区巷道布置 45
5.1 煤层的地质特征 45
5.2 盘区巷道布置及生产系统 45
5.3 盘区车场选型设计 50
6 采煤方法 51
6.1 采煤工艺方式 51
6.2 回采巷道布置 65
7 井下运输 68
7.1 概述 68
7.2 盘区运输设备选择 69
7.3大巷运输设备选择 71
8 矿井提升 75
8.1 矿井提升概述 75
8.2 主副井提升 75
9 矿井通风及安全 78
9.1 矿井概况 78
9.2 矿井通风系统的确定 78
9.3 矿井风量计算 84
9.4 矿井通风阻力计算 89
9.5 矿井通风机的选择 97
9.6 电动机选型 99
9.7 防止特殊灾害的安全措施 101
10 设计矿井基本技术经济指标 103
参考文献 104
专题设计部分
矿井底板突水综合防治技术 105
1 绪论 105
1.1 问题的提出 105
1.2 文献综述 105
2 底板突水机理 113
2.1 底板突水类型的划分 113
2.2 底板突水影响因素分析 114
2.3 底板岩体采动破坏深度计算 117
2.4 完整底板突水极限压力计算 118
2.5 遇断层时底板突水极限压力计算 120
3 底板突水预测 122
3.1 电法突水探测 122
3.2 红外突水探测 123
3.3 同位素突水探测 123
3.4 物探与其他技术联合应用突水探测 124
4 底板突水防治 124
5 结论 125
参考文献 126
翻译部分
英文原文 127
中文译文 138
致 谢 148
|